Victoria Square Development

The landmark Victoria Square development in Belfast City Centre comprises retail outlets and entertainment venues in addition to apartments and a two storey underground carpark.

This £4.2 million piling contract was the largest single piling contract in Northern Ireland in recent years taking place over a year’s duration in a FKL/Stent Foundations joint venture.

Piles were designed for tensile and compressive loads and were installed both inside and outside the 10 metre deep basement. Rock sockets of up to 4 metres underlie clay and gravels.

Piles include:

  • 1219no 600 diameter CFA
  • 125no 750 diameter CFA
  • 132no 750 diameter bored
  • 24no 219 diameter bottom driven mini piles