skip to main content
Back

Ballycastle Health Centre PV system installation

Client
NHSCT
Value
£54,000
Duration
4 Weeks

Key Features

  • Live Hospital Environment
  • Working at Height
  • Project Management
  • Sustainability Project
  • Electrical Installation

H&J Martin completed the PV Installation project at Ballycastle Health Centre as the part of the NHSCT sustainability initiative in what was a challenging project due to the programme, working at height and restricted access space to ensure safe passage around the work area.

Works included installation of solar panels on two sections of flat roof on Ballycastle Health Centre, electrical installation, main connection into the trust main supply via switch room and inverters and the installation of wind deflectors to the panels, due to open nature of the surrounding area.

Your browser is out-of-date!

Update your browser to view this website correctly. Update my browser now

×