Client
SSP
Value
£600,000
Duration
6 Weeks

H&J Martin Fit Out were appointed by Select Service Partners UK to deliver bar facilities “Airside” within the Dublin International Airport T2 Terminal.

Extreme attention and co-ordination was carefully planned, principally to Health & Safety as well as service installations, ensuring the live airport environment and operations were not placed at any risk.

Delivered to a regimented sequence and methodology, the logistics of handling materials, tools and plant as well as co-ordinating manpower within a heavily restricted area of a major international airport, brought a new dimension to programme planning and attention to detail. With the airport functioning 18 hours per day, every day, our workforce rose to the challenge delivering the project on time.