H&J Martin Construction have delivered phase I of the refurbishment and high quality fit-out works of a new aparthotel ‘SACO The Cannon’ situated in a central London City location.
Phase I saw H&J Martin Construction hand over 20 high quality apartments and delivered a new reception area for the new apartment complex building.
The project included extensive works to strip out the existing building including demolition, re-roofing onto the fit-out of the new apartments. The team successfully managed to complete phase I on time despite the fact the demolition team only moved out in November 2015 and part of the building was only roofed in December 2015.
Works were completed over 3 retail units on the ground floor, which remained open during the entirety of the project with minimal disruption.
This phased project at completion will have 79 serviced apartments in total including a communal lounge area which opened in April 2016, and all amenities and rooms are expected to be completed by Summer 2016.