This project involved undertaking batch repairs to the existing taxiway, including AGL upgrade and associated electrical works.
![Bia Laml 01](https://laganmeica.com/assets/casestudies/bia-laml-01.png)
![Bia Laml 02](https://laganmeica.com/assets/casestudies/bia-laml-02.png)
The works were carried out under strict airside access arrangements. The remedial works undertaken included:
- Installation of 68 No. 8” AGL seating pots;
- Completion of 68 No. 500mm stabilisation cores and 68 No. 107mm center cores;
- 1500m of 16mm saw cutting and bituminous sealing for secondary cables and;
- 3000m of saw cutting to pavement edges.
We successfully delivered this project on budget and 3 weeks ahead of schedule.